Community Development DepartmentEngineering

New Buildings / Utility Improvements

Before

After

Lizzie Fountain
Before and After Construction


Under Construction

Galaxy Court Flood Protection and Culvert Replacement Project

City Project No. 2010-29

The Galaxy Court Flood Projection and Trail Culvert Replacement Project will replace a trail crossing over the Arroyo Las Positas at the Springtown Golf Course. It will also replace the metal culverts that convey water beneath the trail.  A concrete box culvert, sufficient to convey 100 year creek flows, will replace the metal culverts. The existing metal culverts are undersized and during the winter months the Arroyo periodically inundates the culverts and overtops the trail.  Overtopping of the trail has resulted in erosion that has undermined the trail and compromised the structural integrity of the culverts and trail crossing.  The restricted flow in the Arroyo causes water to back up through the storm drain system into nearby residential areas and floods the streets, sidewalks and front yards of homes. The proposed project will alleviate area flooding, improve natural habitat and provide a safe trail crossing over the Arroyo Las Positas. The project was awarded to PARC Services, Inc., a Livermore based business, on July 22, 2013.  Construction will commence in June 2014 and should be completed by August 2014.

If you need more information regarding this project, please contact Kevin Duffus, Project Manager, at (925) 960-4556 or via email.

Airport Administration Building

City Project No. 2007-11

The new Livermore Airport Administration Building will replace the existing “Dan Lee” Terminal Building.  The new Administration building will be constructed adjacent to the existing Terminal Building on Terminal Circle, and will be approximately 8,400 square feet.  The Airport Administration Building will provide needed space required by the Airport Administration staff, along with a meeting room, restaurant and concession shell for lease to a private operator. Bids for this project were opened on August 28, 2013 and Diede Construction Inc. (Lodi, CA) was awarded the construction contract with a low bid of $4,078,000.  Construction began in January 2014, with completion scheduled for January 2015.

If you need more information regarding this project, please contact Mike Mikasa, Project Manager, at (925) 960-4533 or via email.

Aeration Basin No. 1 Improvements Project

City Project No. 2011-11

This project includes improvements to Aeration Basin No. 1 at the Livermore Water Reclamation Plant so that it can be put back on line.  Improvements include installing mixers, baffle walls, new spray systems, and gates.  Construction began in July 2014 and is scheduled for completion in January 2015.

If you need more information regarding this project, please contact Joel Waxdeck, Project Manager, at (925) 960-8129 or via
email.
 


Design/Planning Stage

Fire Station No. 9

City Project No. 1994-55

The new Fire Station No. 9 will be located at it's current location at 1919 Cordoba Street at the corner of Concannon Blvd. WLC Architects (Folsom, CA) was awarded the final design agreement for this project in March 2014. Construction for the new Fire Station is scheduled to start in the Winter of 2014 and completed one year later. The project will comprise of the demolition and disposal of the existing 3,350 square foot Fire Station No. 9 and construction of a new 6,920 square foot Fire Station.  Click here to review preliminary plans.

If you need more information regarding this project, please contact Mike Mikasa, Project Manager, at (925) 960-4533 or via
email.

Miscellaneous Storm Drain and Culvert Repairs

City Project No. 2013-25

This project will install a catch basin, about 400' of 12" storm drainline, and a storm drain manhole to alleviate an existing drainage problem on the west side of Greenville Road north of Marathon Drive.  The project is scheduled to bid as part of the Annual Sewer Replacement Project in January 2015 with construction anticipated in Spring 2015.

If you need more information regarding this project, please contact Jim Vingo, Project Manager, at (925) 960-4540 or via
email.

Water Reclamation Plant Electrical Distribution Improvements

City Project No. 2008-48 Phase 2

This project involves replacing the electrical switchgear at the City's Water Reclamation Plant, installing an emergency generator, and running new electrical conduits and cables between the new switchgear and existing motor control centers. The project is scheduled to bid in Fall 2014 with construction between Spring 2015 and Summer 2016.

If you need more information regarding this project, please contact Joel Waxdeck, Project Manager, at (925) 960-8129 or via email.

Annual Sanitary Sewer Replacement

City Project No. 2014-03

This project will replace approximately 10 miles of 8" and 10" sewer mains that are deteriorated and/or undersized.  Most of the work will be conducted in the neighborhood northeast of Livermore High School.  The project is scheduled to bid in January 2015 with construction to follow in Spring 2015.

If you need more information regarding this project, please contact Jim Vingo, Project Manager, at (925) 960-4540 or via email.

Sanitary Sewer Mainline Bottlenecks

City Project No. 1998-74

This project will upsize an existing 12" sewer main that crosses the UPRR tracks south of Brisa St.  The line is expected to be overburdened by the development of the future Brisa neighborhood plan.  The project will alleviate this problem.  The project is scheduled to bid in December 2014 with construction February through April 2015.
If you need more information regarding this project, please contact Jim Vingo, Project Manager, at (925) 960-4540 or via email.



The 2015 Street Resurfacing Project, Project No. 2015-01 will start design soon. Here is a list of streets for the 2015 Overlay.

The 2015 Slurry Seal Project, Project No. 2015-04 is currently under design. Here is a list of streets to be slurry sealed.